Select Facility
-
The facility for which the requisition is configured.
-
Prefix
-
The sequence number of the requisition setup.
-
Next Requisition number
-
The sequence number of the requisition setup.
Note: This number is generated automatically.
-
Notify all Pending Approvers
-
Select this check box to send an email alert to the assigned approvers if a requisition is awaiting approval.
Note: This setting is considered only if the Supervisor Approval or Entity Based Approval option is selected in the Approval Process field.
-
Allow Edit Requisition During Approvals
-
Select this check box to enable users to modify the requisition during the approval.
Note: If this check box is cleared, the requisition cannot be modified during the approval process.
-
Repeat Email for Pending Approvers
-
Select this check box to send repeated email notifications to approvers who have not yet approved the request.
-
Days
-
The duration in which the email notifications must be sent to the approvers.
Note: This setting is considered only if the Supervisor Approval or Entity Based Approval option is selected in the Approval Process field.
-
Approval Process
-
The type of approval process. Possible values:
- RoleBased – Default: Users with the approver role can approve the requisition. This is the standard approval process.
- Supervisor Approval: User with supervisor role can approve the requisition, based on the defined approval limit.
- Entity Based Approval: Users must approve the requisition based on the defined parameters and sequence.
-
Approval Method
-
The process to approve the requisition. Possible values:
-
-
Sequential Override
-
Select this check box to send the requisition to send the requisition for approval to the supervisor.
Note: This check box is displayed only if the Supervisor Approval option is selected in the Approval Process field.
-
-
Mandatory Supervisor Approval
-
Select this check box to mandate the supervisor approval for the requisition.
Note: This check box is displayed only if the Supervisor Approval option is selected in the Approval Process field.
- Parallel: Approvers can approve the requisition in any order.
Note: This option is displayed only if the Entity Based Approval option is selected in the Approval Process option.
- Sequential: Approver must approve the requisition in the same order defined on the Entity Approval Sequence page.
Note: This option is displayed only if the Entity Based Approval option is selected in the Approval Process option.
-
Auto escalate to Next Approver
-
Select this check box to move the requisition to the next approver if the requisition is not approved within the number of days specified in the Consider Records from Past field.
Note: This setting is considered only if the Supervisor Approval option is selected in the Approval Processfield.
-
Consider Records from Past
-
The number of days from which the requisition must be moved to the next approver.
Note: This field is enabled only if the Auto escalate to Next Approver check box is selected.
-
Retain Days
-
The number of days a requisition must be retained with a user before moving to next approver.
Note: This field is enabled only if the Auto escalate to Next Approver check box is selected.
-
Allow Value Below
-
The maximum requisition amount below which the application automatically forwards the requisition to the next approver, if the approval is delayed.
Note: This field is enabled only if the Auto escalate to Next Approver check box is selected.