Setting up the approval process for supplier onboarding application
Use this page to define the hierarchy for the approval of the Onboarding application.
- Select Supplier Onboarding > Onboarding Setup.The Onboarding Setup page is displayed.
- Click Approval Settings tab. The New Vendor and Existing Supplier tabs are displayed.
- Specify this information:
- Approval Sequence
-
The approval method for the application submitted by the vendor.
- Parallel: More than one group can approve the application simultaneously.
- Serial: Only one group can approve the information related to a particular entity at a time, based on the defined sequential order.
- Approval Override Allowed
- Select this check box to override the approved settings.
- Click Save. The approval sequence setting is saved.
- Specify this information on the New Vendor and the Existing Supplier tabs:
- Sequence
-
The sequence in which the onboarding application must be approved.
Note: This value is defaulted. and is incremented by 1 when the Approval Sequence is set to Serial.
- Group Name
- The name of the approval group.
- Stage
-
The phase for the execution of the approval process. Possible values:
- Both
- Qualification
- Selection
Note: This field is displayed only when the Onboarding Style is set to Two step. - Approver
- Select this check box to enable the approval group to authorize the onboarding application.
- Override
- Select this check box to override the decision of other approval groups.
- Click Save.