Specifying the action informations
- Select . The View Defective Material Notices search criteria page is displayed.
- Specify the criteria.
- Click Continue. The Defective Material Notices page is displayed.
- Click Edit corresponding to the DMN on the Pending DMNs tab. The DMN Edit page is displayed.
- Specify this information on the Action Information tab:
-
Containment Response Required
-
Indicates that the containment plan is required to isolate the problem.
-
Containment Response Due Date
-
The due date to publish the containment action plan.
-
Containment Plan
-
The description of the containment actions to isolate the impact of the problem.
-
Containment Date
-
The date on which the containment plan is published.
-
Containment Status
-
The status of the containment action plan. Possible values:
-
Customer Feedback
-
The customer feedback for the containment action plan.
-
Root Cause
-
The potential cause of the problem.
-
Corrective Response Required
-
Indicates that the long-term measure (corrective action) is required to prevent the occurrence of the problem.
-
Corrective Response Due Date
-
The due date to publish the corrective action plan.
-
Corrective Plan
-
The corrective action plan with details of all the phases of the problem-solving process.
-
Corrective Date
-
The date on which the corrective action plan is published.
-
Corrective Status
-
The status of the corrective action plan. Possible values:
-
First Corrected Shipment Date
-
The date on which the first shipment with the corrected parts is sent.
-
Customer Feedback
-
The customer feedback for the corrective action plan.
-
Customer Template
-
The customer-defined template used for the containment or corrective action form.