Responding to the inspection request
Use this page to respond to the inspection request submitted by the supplier.
Note: You can use the Reject option, to reject the inspection line.
- Select Source Inspection > Inspections. The Inspections page is displayed.
- Click View. The Inspection details page is displayed.
- Review this information:
- Facility
- The location from where the inspection request is created.
- Supplier
- The name of the supplier who created the inspection request.
- Contact
- The contact details of the supplier.
- Inspection Type
- The type of inspection.
- Request Create Date
- The date on which the request is created.
- Target Date
- The last date for responding to the inspection request.
- Click Accept. The inspection process is initiated.
Note: The status of the inspection request is modified to In Process.
- Click the view icon on the Inspection Line tab. The Inspection Line page is displayed.
Note: You must perform the inspection for each line separately.
- Specify this information:
- Accept Quantity
- The number of parts accepted in the inspection.
- Accept Under Deviation Quantity
- The number of parts accepted with some deviations in the inspection.
- Reject Quantity
- The number of parts rejected in the inspection.
- Total Accept Quantity
- The total number of parts accepted in the inspection.
- Reject
- The serial number of the part rejected in the inspection.
- Reject Reason
-
The reason code to reject the part.
Note: The customer can approve more quantities than the inspected quantity only if the Allow approved quantity greater than Inspection quantity check box is selected on the Inspection Setup page.
- Click Submit.
Note: You can add a non-conformance code using the Add option on the Non-Conformance Code tab.