Defining the search criteria for Schedules Weekly Summary

Use the Schedules Weekly Summary page to specify the search criteria for the weekly summary that is displayed on the Schedules Weekly Summary list page.

  1. Select Demand > Schedule Weekly Summary. The Schedule Weekly Summary page is displayed.
  2. Specify this information:
    Supplier
    The name of the supplier
    Facility
    The name of the location for which the schedule summary is required.
    Ship To
    The name of the location from where the demand for the parts is raised.
    Start Week
    The week when the summary schedule starts.
    End Week
    The week when the summary schedule ends.
    Include Past Due
    If this check box is selected, the shipments that are due before the start date is displayed.
  3. Click Submit. The Schedule Weekly Summary details page is displayed.