Adding or modifying PPAP discrepancy information

Use the Edit Production Part Approval page to specify or modify the part discrepancy details for the Production Part Approval Process (PPAP).

  1. Select PPAP > Create PPAP.
  2. Click Continue. The Production Part Approval Process is displayed.
  3. Click Add on the Discrepancy Information tab. The Add Discrepancy Detail page is displayed.
  4. Click Edit corresponding to the item to modify an existing discrepancy details,. The Edit Discrepancy Detail page is displayed.
  5. Specify or modify this information:
    Item
    The code of the part.
    Required
    The quantity of the part required.
    Actual
    The quantity of the part received.
    Date
    The date on which the discrepancy is identified.
  6. Click Add or Update. The Production Part Approval Process page is displayed.