Defining cycles - Calendar tab
You must specify this information in the Calendar tab.
- Calendar
- The calendar (hierarchy) that is used by this cycle.
See,Calendars overview.
- Calendar Level for Storing Scenario Values
- The calendar level in which scenario plan data is reported. Possible
values:
- Years
- Quarters
- Months
- Weeks
Note: If the Enable Telescopic option is set to On, this value is the parent level from which telescopic bucket can be generated. - Future Horizon
- The number of periods in future (from the current planning period) used to store plans
based on the calendar level.Note:
- If the selected calendar hierarchy does not extend to include the required horizon for the created cycle period, the periods in future are created only within the hierarchy.
- If the Enable topic option is set to On, this value is considered as the overall horizon size.
- History Horizon
- The number of history periods, prior to the current planning period, used to store
plans based on the calendar level.Note:
- If the selected calendar hierarchy does not extend to include to the required horizon for the created cycle period, the history periods are created only within the hierarchy.
- If the Enable topic option is set to On, this value is considered as the overall horizon size.
- Enable Telescopic
- Allows the user to determine the levels within the calendar level for storing the
required telescopic Scenario valuesNote:.
- By default, this value is set to Off.
- If this option is set to On, Telescopic Levels table is displayed.