Program scope
The TFORM_CALC_RESOURCE_CAPACITY program determines the scope as follows:
The program processes the following tables to generate capacity hours for resource and resource unit:
- SC_CALENDAR
- SC_CALENDAR_PERIOD
- SC_SHIFT_PATTERN_LINE
- SC_RESOURCE
- SC_RESOURCE_UNIT
- SC_RESOURCE_RELATION
- SC_RESOURCE_SHIFT_PATTERN_ADJUSTMENT
- SC_RESOURCE_UNIT_SHIFT_PATTERN_ADJUSTMENT
- SC_RESOURCE_SHIFT_ADJUSTMENT
- SC_RESOURCE_UNIT_SHIFT_ADJUSTMENT
- SZ_SCP_CALENDAR
The program updates the following tables with capacity hours for each shift:
- SC_RESOURCE_SHIFT_CAPACITY
- SC_RESOURCE_UNIT_SHIFT_CAPACITY