Scheduling process batches
- Select the required process batches on the planning board.
 - Select Schedule > Schedule Process Batches. The Schedule Process Batches window is displayed. 
           Note:
- The fields are displayed based on the features enabled on the Features tab of the Global Preferences screen.
 - The title of the Schedule process batches window displays type of batches scheduled. For example:
               
- When you select batches from the planning board, the title displayed as Schedule process batches (selection).
 - When you access from the Create Inflow window for ordersof an end stage, the title displayed as Schedule process batches (end product batches).
 - When you access the Create Inflow window for coupled batches, the title displayed as Schedule process batches (coupled batches).
 
 
 - Select the required value in the schedule batches field. Possible values:
           
- As soon as possible
 - Just in time
 
 - Select a start or finish time in the from or until field. 
           
This field is displayed based on the value selected in the schedule batches field.
Note:- If this field value is selected as other, you must specify the time within the work area. Else, the system does not provide a solution.
 - Downtime is determined based on the value specified in the start of first batch or end of last batch field.
 
 - Select the order of the batch in the fixed sequence field, if required.
 - Select the optimize sequence check box to identify the suitable order, if required. 
           Note: If this check box is selected, the Optimize tab is displayed.
 - Specify this information:
           
- Time limit (seconds)
 - The duration for AI optimization to optimize the schedule.
 - Balanced weights
 - If this check box is selected, the algorithm determines a set of objective weights automatically.
 - User defined weights
 - If this check box is selected, you can define the weights based on requirements.
 
 - Select the strict sequence (do not fill gaps) check box, to maintain the current sequence without gaps. 
           Note: If this check box is not selected:
- The sequence can change for better process utilization.
 - The start where stopped (+ and - only) option must not be selected.
 
 - Select the constraint in the not after or not before field. 
           Note:
- This field is displayed based on the value selected in the schedule batches field.
 - This field ensures batches are not placed beyond the selected bound.
 
 - Select the keep within work area check box, to schedule batches within the work area.
 - Select cycle, if defined. 
           
Batches are scheduled based on the value selected in the schedule batches field.
Note:- If enough time is not available to schedule all batches in the cycle, the remaining batches are scheduled outside the selected cycle.
 - If the always keep within cycle check box is selected, batches are scheduled within the selected cycle even if there is an overlap.
 
 - Select the resource availability check box, to ensure that the resource availability is not exceeded when scheduling batches. 
           Note: The system does not consider batches when a resource is unavailable.
 - Select the enabling batches check box, to enable resource capacity when scheduling batches.
 - Select the utilities check box, to ensure utility capacity is not exceeded when optimizing the schedule. 
           Note: The system considers only critical utilities selected in the Utility window, which can be accessed from the Utilities screen of the Factory menu.
 - Select the inventory constraint check box, to maintain stock levels within limits for specific decoupled products.
           Note: This check box is applicable only for decoupled products with the enable inventory constraint option selected. This option is displayed on the Inventory Point tab of the Inventory menu.
 - Select the keep allocation check box, to retain batches on the selected resource.
 - Specify the resource allocation for selected batches in the allocate to field, if required.
 - Click Apply to preview the effects on the planning board.