Changeover tab
- Define the standard changeover.
 - Select the corresponding check box if the changeover after idle time is not standard. 
           Note:
- If the check box is selected, the changeover after idle time is considered when calculating the changeover time for tank batches.
 - You must move to non-standard changeover at resource when creating resources, if required. This can have severe performance penalties for the Solver when a utility or enabling claim on changeover or setup is available.
 
 - Specify the time for the changeover after idle time and the changeover idle time in the corresponding fields if you have specified a non-standard changeover after idle time.
 - Specify the changeover constraint.
 - Specify the duration settings, if required. You must perform these actions: 
           
- Click Select in the duration matrices section.
 - Double-click the duration matrices in the available items section of the Transition Matrix Selection window box that you require to include and click OK.
 - Click Select in the duration rules section.
 - Double-click the duration rules that you require to include in the available items section of the Transition Rule Selection window and click OK.
 - Select a calculation formula for the selected duration matrices and duration rules from the duration formula list.
 
 - Specify the cost settings, if required. 
           
- Click Select in the cost matrices section.
 - Double-click the cost matrices in the available items section of the Transition Matrix Selection window that you require to include and click OK.
 - Click Select in the cost rules section.
 - Double-click the cost rules in the available items section of the Transition Rule Selection window that you require to include and click OK.
 - Select a calculation formula for the selected cost matrices and cost rules from the cost formula list.
 
 
           Related topics