Adding Replenishment Engine orders – Production
Production Transactional data are measures mapped as Order Type in the Replenishment engine, for the Cycle. These are the production order types:
- Fixed Production Orders
- Planned Production Orders
- Scheduled Production Orders
- Firm Production Orders
You can add Replenishment Engine Orders of type ‘Production’ for the Transactional data measures mapped to Production Orders in the Replenishment Engine assigned to the Cycle.
-
Right click a transactional data measure which is mapped to a Production Order.
The Add Production Order menu is
displayed.
Note: The Add Production Order menu is displayed only if:
- The measure is of Transactional Data (Transfer) type.
- The Transactional data measure is defined in the Replenishment Engine.
- The Replenishment Engine is assigned to the Cycle.
- The transactional data measure is mapped to a Production Order types defined in the Replenishment Engine.
- The user has permission to add the transactional data.
- The scenario can be edited by the current user (part of share).
- Select Add Production Order A new window is displayed.
- Specify this information:
- Name
- The name of the transactional data.Note: This value is defaulted based on the selected Transactional Data measure.
- Source measure
- The source measure of the Production Order. This value is derived from the transactional data name.
- Destination measure
- The destination measure of the Production Order. This value is derived from the transactional data name.
- Process Item
- The item to be processed.Note:
- This value is selected from a list of Process Items within the current context derived using the Processes - Item attribute in the Engine Supply Allocation Mapping.
- If the context is at a valid Process Item, the value is pre-populated.
- Process Location
- The Location where the item is to be processed.Note:
- This value is selected from a list of Process Locations within the current context, derived using the Processes - Location attribute in the Engines Supply Allocation Mapping.
- If the context is the base location, the value is pre-populated.
- The available options are based on the value specified for Process Item.
- Process Version
- The Process Versions applicable for the selected Process Item and Process Location.Note: The available options are based on the value specified for Process Item and Process Location and derived using the Processes - Process Version attribute in the Engines Supply Allocation Mapping.
- Quantity
- The value of the Production Order.
- Critical Flag
- Indicates the criticality of the Production Order.Note: By default, this value is set to None and is read only.
- Start Date
- The start date of the production process.Note:
- If Transactional data
Enable Lead Time is set to On:
- This value is populated with ‘End date of the selected cell – Lead Time’.
- This value is populated when the values for Process Item, Process Location and Process Version fields are specified.
- The End Date is updated as ‘Start Date + Lead Time’ at the time of modifying the populated value.
- If Transactional data
Enable Lead Time is set to Off:
- This value is populated with the ‘End date of the selected cell’.
- The End Date is not updated when you modify the populated value.
- If Transactional data
Enable Lead Time is set to On:
- End Date
- The end date of the production process.Note:
- This value is populated with the 'End Date of the selected cell'.
- This value is populated when the values for Process Item, Process Location and Process Version fields are specified.
- If Transactional data
Enable Lead Time is set to On:
- The Start Date is updated as 'End Date – Lead Time’ at the time of modifying the populated value.
- If Transactional data
Enable Lead Time is set to Off:
- The Start Date is not updated when you modify the populated value.
- Lead Time
- Indicates the Lead Time for the Production process. This is
defined in the Engine (Transfer Lead Time) parameter in Transfer Out Mappings tab.Note:
- This field is displayed only if Transactional data Enable Lead Time is set to On.
- This value is populated when the values for Process Item, Process Location and Process Version fields are specified.
- This value is set to zero, if Lead Time is not defined in the Engine.
- Need Date
- The default value is set as End Date. However, you can modify the value.
- Note
- The additional information (text note) related to the Production Order.
- Reference
- The reference text related to the Production Order.
- Custom Field 1 to 5
- The additional text used as reference for the Production Order. These fields are displayed based on the configuration of the transactional data definition.
- Click Save.