CIP rules
A CIP step is associated with a rule. This step is used to create a CIP batch with the default step quantity.
This table shows the various types of CIP rule:
Rule | Description |
---|---|
Absolute time |
A CIP batch can be scheduled after the time T when this condition is verified: The duration T minus the start of a batch that follows the last CIP batch exceeds a specified duration. |
Number of batches | A CIP batch can be scheduled after a specified number of batches since the last CIP batch. |
Processing time |
A CIP batch can be scheduled when the sum of the process segment durations since the last CIP exceeds a specified duration. Processing time is used to schedule a CIP batch after the resource has been used for a specified period of time. Unlike absolute time, processing time does not count the resource's idle time, for example, the time between process batches. |
Quantity | A CIP batch can be scheduled when the sum of the batch quantities since the last CIP exceeds the specified quantity. |
Transition cost |
A CIP batch can be scheduled when the sum of the transition costs since the last CIP exceeds the specified quantity. If the duration or quantity of a batch is not considered; however, specific events require a CIP batch, you can use a cost matrix for modeling. Each batch contributes to the sum of the transition costs since the last CIP. The contribution of a batch is determined by the changeover cost to the corresponding batch. The cost of the first batch on a resource is determined by the gauge cost, or zero if no gauge cost is specified. The cost of the last batch on a resource is the transition of the batch criterion to NONE. |
These are the limits or constraints for CIP modeling:
- Minimum
The minimum duration, number, or quantity determines the minimum number of process batches that must be scheduled after a CIP batch. This constraint can only be used for these rule types:
- Quantity
- Processing time
- Number of batches
Note: This constraint is not used when the value is set to zero. - Maximum
The maximum duration, number, or quantity determines the maximum number of process batches that can be scheduled after a CIP batch.
- Resetting the CIP count for large changeovers
If large changeovers occur, you can run a CIP operation during these large changeovers. During a large changeover, although the actual CIP batch is not scheduled, the CIP operation is performed in the factory.
If this option is enabled and a minimum changeover duration is defined, the CIP counter is reset by the solver each time a large changeover occurs. However, CIP batch is not scheduled. This option is not applicable for absolute-time CIP rules.
The gauge time and value can be used to specify a start value at a certain point in time for the CIP calculation.
These conditions are applicable for
calculations:- If a CIP rule's gauge date is defined, the solver calculations start from the specified point in time, using the specified gauge value.
- If no gauge date is defined, the solver calculations start from the end of the last CIP batch on that resource, considering the starting value as 0.
- If CIP batch is not assigned to the resource, the solver calculations start from the beginning of the work area.
- If the CIP rule type is set to Absolute time and gauge date is not defined, the solver calculations start from the beginning of the first batch after the work area.
A resource's batch count rule specifies that a CIP batch must be placed after every 20 batches. At 9:00 A.M. the CIP batch scheduling for the day starts. At this moment in time, five batches that are not in the planning board have already been processed for this resource. In the planning board, the next CIP batch must be placed after the fifteenth process batch instead of the twentieth. To define these five batches as a start value, you can specify this information.
- The current date as the gauge date
- The gauge time 9:00
- The gauge batch count 5
The CIP solver calculations start from 9:00 A.M. onward, using 5 as a start value.