Creating downtime
- Select Batches > Downtime. The Downtime overview window is displayed.
- Click New to create a new record. The Downtime Entry window is displayed.
-
Specify a relevant remarks in the Remarks field of the entry window.
Note: If remarks are enabled in the view settings, the remarks are displayed on the planning board.
- Select the resource to which the downtime is applicable.
-
Clear the Locked check box if you
require to move the batch manually in time.
Note: Unlocked downtime batches are not affected by automatic scheduling functions.
-
Select a start time and duration for the batch.
Note: If you modify the start time, the end time is changed automatically and the duration remains the same. If you modify the duration, the start time remains the same and the end time is adjusted.
- Click OK to save the batch and close the entry window.
Related topics