Resource claim tab

  1. Click the Resource claim tab.
    Note: 
    • The claim for resources from enabling resource groups must be specified separately for each resource group in which the resource is displayed.
    • The Resource claim tab is disabled if the resource group is an enabling, since enabling groups cannot claim other enabling resources.
  2. Click Select to select an enabling resource group and corresponding resources.
    Note: The first column of the Resource Claim table is a tree view that displays the claimed enabling resource groups in level one. The children at the level below, represents the resources linked to the current resource group.
  3. Indicate the batch segments such as default, setup, outflow and changeover In the remaining columns during which the enabling resource group must be claimed.
    The claims behind the enabling resource groups (tree level 1) represent the default claim for the resources in the current resource group. The claims behind the resources (tree level 2) represent the actual claim for the enabling resource group for that specific resource.
    Note: 
    • Double-click in a segment cell to claim the segment (a check mark appears in that segment). Double-click in the segment cell to cancel the claim.
    • If a claim for an enabling resource group (tree level 1) is modified, the claim for this segment overwrites the existing segment claim of all lower level resources. Modifications of a claim at the resource level (tree level 2) only affects the segment claim for that particular resource.