Options tab
-
Select the
time period where resource is
unavailable,
downtime, and
locked and unselected
batches check boxes, if you require splitting to take place when a
batch coincides with any of these items.
Clearing these check boxes can lead to batch overlap.
- Select maximum duration to split the batches at the maximum batch duration of the resource.
-
Perform these operations to enable the process batches to be
joined:
- Select the with joining check box.
-
Select
adjacent only and
select one of the following options to join overlapping batches as adjacent
batches:
- adjacent if within
- To join overlapping batches, select this option and specify the overlapping interval.
- adjacent if successive
- To join only successive batches, select this option.
- Select linked only to join linked batches only.
- Select on same resource only to join only batches that use the same resource.
-
Select
use cycle and select a
cycle to join batches together in a period.
If you select this check box, the batches that belong to the same cycle period are joined.
-
Select
if field values are
same and select a field to join batches on fields of any related
order.
The search method for the related order is the same as for any related order in the interfaces. If several orders are connected, the first order that is filled by the selected batch is considered only.
- Click Apply to view the change results in the planning board.