General tab

  1. Specify a description for the utility.
  2. Select a timetable from the list.
  3. Select a type of utility required from the type list.
    Note: You can also specify a new code.
  4. Select the unit of measure for the utility.
  5. Specify a maximum and minimum claim and a claim increment.
  6. Select the is critical check box to include this utility when utilities are included in a solver. In addition, critical utilities are indicated on the planning board with a bold red line.
  7. Select the check schedule check box if this utility is to be verified when you run the Check schedule function.