Parameters tab

This tab is displayed only if the value for entity is set to bucketizer, inventory level, or resource utilization export and the interface mode is set to write.

  1. Select the reference point from the list.
    Note: 
    • If you select other option from the list, define a date and time in the fields below.
    • The normal reference point is the start of the work area.
  2. Specify the number of buckets to be exported in the count field.
  3. Specify the duration and unit of time for each individual bucket.
  4. Assign an identifier offset, if the bucket to be labeled with a different day from the day on which it actually begins.
    Note: If your external system specifies buckets beginning at a point in time that does not coincide with your reference point selection, you can use the method options to force exported data into buckets beginning at a different point in time. For example, while you can prefer to use a work area beginning at 00:00:00 every Monday in Infor Production Scheduling, another system can begin the working week at 00:00:00 on Sunday.
  5. Use the Select option to select the resource groups to which you require to apply this entity. The Resource Group Selection window is displayed.