Creating a transition rule

  1. Select Factory > Transition Rules. The Transition Rules overview window is displayed.
  2. Click New. The New Transition Rule window is displayed.
  3. Specify a unique code for the transition rule.
  4. Specify the transition rule type.
  5. Click OK. The Transition Rule Entry window is displayed.
  6. Specify a description in the entry window.
  7. Select one of the entities to which this rule can be applied from the entity list. Possible values:
    • process batch
    • process step
    • order
    • end item
    • tank batch
  8. Select a field from the field list. The items displayed in the field list are fields available in the entry window for the entities, therefore change is based on the entity selected.
  9. Specify values in the if field values are same and the if field values are different fields. The former is used to indicate a brief cleaning procedure and the latter to run a full-scale procedure.
  10. Click OK to save the rule and close the entry window.