Strict sequence when scheduling process batches
The Strict sequence (do not fill gaps) option is used if you require to fix the current sequence. If you select this option, the selected sequence is not interrupted, even if the sequence contains gaps that are large enough for other batches to fit in. If you do not select this option, the sequence can be changed where that leads to better process utilization. If resources are in both choice and combination groups, gaps may occur in process utilization. Infor Production Scheduling tries to fill these gaps. If there are variable changeover times (changeover matrices or changeover rules), the changeover times are recalculated to consider the new sequence.