Dashboard
Use the dashboard to view the Key Performance Indicators (KPIs) name and the related values for each week. You can track the downtime of resources using KPIs.
The KPIs for the current schedule are compared with a baseline. When you open the dashboard, a baseline is automatically created as a snapshot. However, you can create a snapshot manually.
These are the examples describing KPIs:
- Production cost: This value is calculated based on the data defined on the Resource Groups tab of the Process Step Entry window.
- Production time: If this value decreases since the last snapshot, the difference is indicated with green. If the value increases since the last snapshot, the difference is indicated with red.
The combination of two KPIs can enable you to detect issues or conflicts. For example:
- Resource conflicts
- Late orders
These background colors are displayed for late orders KPI:
Color | Description |
---|---|
Red | High alert |
Yellow | Medium alert |
Green | No alert |
You can select Infor Production Scheduling, the dashboard is automatically displayed when you restart the application.
from the menu to view the dashboard below the planning board. If the dashboard is displayed when you exitYou can use these options that are displayed at the bottom of the
:- : To collapse all nodes and hide the KPIs.
- : To expand all nodes and display the KPIs.
- : To create a new snapshot. This snapshot replaces the previous snapshot.
- : To discard the changes made to the schedule since the last snapshot.
- : To configure the dashboard. You can select the KPIs that you require to view in the global display settings and alerts for late orders.