Publish tab

  1. Select the publish view check box. The schedules for which the publish view check box is selected are available in Web Viewer.
  2. Specify the time period to be displayed when the schedule is published in Web Viewer. Perform these actions to view the published schedules in Web Viewer:
    • Specify a start time by providing the number of days, weeks, or months, and the reference point in the start fields. You can specify a positive or negative integer.
      • Specify a duration in the by providing a number to indicate the number of days, weeks, or months. You can select days, weeks or months for the time interval in the corresponding fields.
    • You can specify an integer greater than zero.
      Note: When the specified start date or period is in conflict with the start and/or end of horizon, the start date and/or period of time for the picture to be published is corrected, therefore this cannot exceed the boundaries of the horizon.
  3. Select a value from the picture width list.
    Note: The value you select is the width in pixels of the picture that is displayed in Web Viewer. Standard values are displayed in the list. If you select other option, you can specify an integer between 100 and 4000.
  4. Select the publish PDF option to publish views in the PDF format.
    Note: The PDFCreator must be installed. You can download this program from the Sourceforge.net URL.
    Note:  This table lists the required PDFCreator version:
    Production Scheduling version PDFCreator version
    5.4.00 0.9.3
    5.4.01 and 5.4.02 0.9.6
    5.4.03 to 5.4.06 0.9.8
    5.4.07 to 5.4.09 0.9.9
    5.4.10 1.0.2
    5.4.11 1.1.0
    5.4.12 and 5.4.13 1.2.0
    5.4.14 to 5.4.17 1.2.2
    5.4.18 1.4.2