Downtime
Downtime on a resource is the total duration of time within the work area taken up by maintenance and other irregular interruptions. Downtime is represented by simplified batches. If batches overlap with downtime, this is indicated in the planning board and in the Check Schedule.
Schedule process batches considers downtime. A status can be assigned to the downtime batches and is locked by default.
Note: It is recommended to create separate downtime for each resource, instead of combining
process and tank downtime.
This image displays a downtime batch for maintenance, in the planning board, corresponding to a normal process batch.
Note: You can specify the data to be displayed with the batch on the planning board when
creating a view.