Demand Planning

To import master data for Demand Planning and create Cycle period, these macros must be executed.

  1. Execute the Demand - Import Master data from SCV macro. You must wait until planning hierarchies complete the building process.
  2. Execute the Demand - System Macro (PW) to initialize the system and create a Cycle Period macro to create a Demand business cycle with periodicity of Part-weeks.
    Note: To create cycles with different periodicities select the appropriate alternative macro. For example, Weekly periodicity, execute the Demand - System Macro (W) to initialize the system and create a Cycle Period macro.