Defining cycles - Calendar tab
You must specify this information in the Calendar tab.
	 - Calendar
 - The calendar (hierarchy) that is used by this cycle.
See,Calendars overview.
 - Calendar Level for Storing Scenario Values
 - The calendar level in which scenario plan data is reported. Possible
              values:
- Years
 - Quarters
 - Months
 - Weeks
 
Note: If the Enable Telescopic option is set to On, this value is the parent level from which telescopic bucket can be generated. - Future Horizon
 - The number of periods in future (from the current planning period) used to store plans
            based on the calendar level.Note:
- If the selected calendar hierarchy does not extend to include the required horizon for the created cycle period, the periods in future are created only within the hierarchy.
 - If the Enable topic option is set to On, this value is considered as the overall horizon size.
 
 - History Horizon
 - The number of history periods, prior to the current planning period, used to store
            plans based on the calendar level.Note:
- If the selected calendar hierarchy does not extend to include to the required horizon for the created cycle period, the history periods are created only within the hierarchy.
 - If the Enable topic option is set to On, this value is considered as the overall horizon size.
 
 
- Enable Telescopic
 - Allows the user to determine the levels within the calendar level for storing the
            required telescopic Scenario valuesNote:.
- By default, this value is set to Off.
 - If this option is set to On, Telescopic Levels table is displayed.