Distributing resource usage

After recording resource usage for a group project or group inspection, you can distribute that usage among one or more of the individual work orders or inspections belonging to the group. If you distribute resource usage by count, Infor Public Sector will divide the usage equally among all of the selected work orders or inspections. For asset types with measured lengths, such as sewer mains, you can also distribute usage by asset length. In that case the usage will be distributed according to the lengths of their associated assets.

  1. Load the group project or group inspection you want into the appropriate InfoViewer.
  2. Select each work order or inspection to which you want to distribute resource usage.
  3. Click the Action button and select Distribute Usage by Count or Distribute Usage by Asset Length.
    Infor Public Sector shows a message indicating how the usage will be distributed and asking if you want to continue.
  4. Click Yes.