Work orders

The Work Orders node in the Resource Manager tree shows information on your work orders. The work orders are displayed in the Work Order grid when you select the Work Orders node. There is also a subnode for each work order. Each work order node has two subnodes:

  • Scheduled: Lists the employees, equipment, and vehicles that have been scheduled for the work order.
  • Costs: Lists the labor, equipment, material, and vehicle costs for the work order.

Work orders can be added to the Resource Manager in three ways. First, the list always includes all work orders that are assigned to you. Second, the list includes all work orders that belong to group projects that you have added using the Group Projects node. Finally, you can add work orders to the list manually, either by adding an existing work order or creating a new work order.