Projecting a line item penalty

If you want to know the potential penalty amount for an unpaid line item at a future date, you can project the penalty. This is helpful if a customer asks what the penalty will be if he or she waits a certain number of days before paying a charge. You can also use the Bill InfoViewer to project penalties for an entire bill.

  1. Load the line item you want into the Line Item InfoViewer.
    You access the Line Item InfoViewer by clicking the Line Item link for the line item on the Bill InfoViewer's Line Item tab.
  2. Click Project Penalty in the upper right corner of the viewer.
  3. Specify a date in the Project Penalty Through field.
  4. Click Project
    Infor Public Sector indicates that the projected penalty run was successful and shows the dollar amount of the penalty as of the specified date.
  5. If you want to project penalties for any other dates, specify a new date and click Project for each additional penalty.