Specifying resource quantities
After adding resource types to your plan, you can specify the number of resources of each type that are available, such as 1000 hours of electrician labor time over the duration of the plan. You can specify the resource quantities for the entire length of the plan, as shown below, or you can specify the number of resources available for each month of the plan.
If you specify a total quantity for the plan, Infor Public Sector automatically calculates the amount per month. For example, if you need laborers to work 80 hours over the course of a two-month plan, Infor Public Sector enters 40 hours of work for each month of the plan. If you want to enter different amounts for each month, such as 50 hours for the first month and 30 for the second, you can enter the monthly quantities separately.