Configuring replenish days value
- Select Par Counting in the Par and Cycle Counting menu.
 - 
        Select Configuration > Replenish Days.
        
The Configure Replenish Days page is displayed. Define the number of replenish days to be used for the computation of the suggested level value. Default value is '1'
 - Select the Inherit check box to apply the settings for replenish days value or clear to assign individual settings.
 - 
        Click Save.
        A confirmation page is displayed.
 - 
        Click Done.
        Note: If the Replenishment days is modified after the Inbound Master Scheduler has run, the system will re-compute for the SPL using the new replenishment days value when these conditions are satisfied:
- Inbound Master Scheduler runs again.
 - New transaction is created after the Inbound Master Scheduler last ran.