Running productivity reports
Use this procedure to run reports containing productivity statistics for a specified time period grouped by Activity or Operator.
To run the team productivity report
- 
        Select Global Reports from the Administration menu.
        
The Global Reporting page appears.
 - Click Productivity to display the list of reports, if it does not already appear.
 - 
        Click Productivity Report.
        
The Productivity Report Settings page appears.
 - 
        Consider the following fields.
        
- Application
 - 
                
Select the application for which you want to view user productivity.
 - Operator
 - 
                
Select the operator that you want to view in the report.
 - Group By
 - 
                
Select to group report by operator or by activity.
 - Report Start Date
 - 
                
Enter or select a start date to include events for the selected operator during a specific date range.
 - End Date
 - 
                
Enter or select an end date to include events for the selected operator during a specific date range.
 
 - 
        Click Run Report to generate the report.
        
The Productivity report appears on the Report Viewer page.