Configuring replenish days value
- Select Par Counting in the Par and Cycle Counting menu.
 - 
        Select Configuration > Replenish Days.
        
The Configure Replenish Days page is displayed. Define the number of replenish days to be used for the computation of the suggested level value. Default value is '1'
 - Tick the Inherit box to apply the settings for replenish days value or untick to assign individual settings.
 - Click Save. A confirmation page is displayed.
 - 
        Click Done.
        Note:
If the Replenishment days is modified after the RQTransactionSyncScheduler has run, the system will re-compute for the SPL using the new replenishment days value when the following conditions are satisfied:
- 
                
RQTransactionSyncScheduler runs again
 - 
                
New transaction is created after the RQTransactionSyncScheduler last ran
 
 -