Flagging the work as finished
- Select an operation.
-
Tap or click the status then select Finish
Work.
A prompt is displayed when there are still pending time reports that are not yet submitted to the back office. The prompt displays time reports with these status:
- 0: Draft
- 9: Split
- 10: Definite
- 15: Rejected
Preliminary miscellaneous cost lines displays a prompt to notify user that there are pending miscellaneous cost lines that are not yet submitted to the back office.- 10: Preliminary
-
Optionally, the user can submit the pending time reports to the back office or not to
proceed with setting the operation status to Finish Work.
A prompt is displayed when there are events like:
- unfiled service error report
- unreported inspection tasks
- unreported safety inspection tasks
- unreported required meter readings
- failed time transactions
- pending time reports
- pending material lines