Example
A maintenance work is scheduled for the 15th of a month. The advanced warning period is seven days. The order displays as pending on the 8th.
Scenarios for missed work
Work can become missed under these scenarios:
- Scenario 1: When the schedule is configured to expire at the end of the period, and the period type is day, the work becomes missed at the end of the scheduled day, which in this example is the 15th.
- Scenario 2: When the schedule is not configured to expire at the end of the period, and the scheduling window is seven days, the work scheduled for the 15th becomes missed on the 22nd of the month.
- Scenario 3: When the schedule is configured to expire at the end of the period, and the period type is month, the work becomes missed at the end of the month.