Intermediate material validation

Intermediate material validation ensures that inventory packs that are still in progress can continue through the required production operations. The validation considers the inventory pack material and its Next Routing Operation, including scenarios involving co-production and phantom operations.

An inventory pack of intermediate material is an inventory pack that has not completed all operations. When such an inventory pack is consumed, the inventory pack material being consumed appears to be the same material as that being created. Therefore, standard BOM validation does not apply.

To support this scenario, the application first checks whether the inventory pack is a work-in-progress, by verifying its Next Routing Operation. If the value is not empty, then a slightly different validation is carried out:

  • The inventory pack material is the same as the production order material.
  • The Next Routing Operation is an operation performed by the machine where the inventory pack is being consumed.

If either validation fails, the application prevents the transaction with an error.

Intermediate material validation and phantom operations

Co-production processes, run against a Recipe Production Order and the inventory packs that are output are received against one or more Receiving Production Orders. If the inventory pack being input is an intermediate material whose Next Routing Operation is not empty, then the material number of the input inventory pack is not the same as the recipe job material. Thus, inventory fails the validation.

To support this, the application further checks that if the production order material is a recipe, then the inventory pack’s Next Routing Operation is marked as a Phantom. Phantom indicates that the operation is performed on a Recipe Production Order. See .