Active Positions

Active positions are used to support manufacturing processes that create multiple inventory packs of same material from a single input material, such as slitting processes. The use of co-production in such scenarios adds a layer of complexity that should be avoided when possible. Active positions must be used in such scenarios, as they provide a simpler approach for managing the creation of multiple inventory packs during a production run.

The number of active positions determine the number of positions that inventory is created during a production run. These active positions are a subset of the inventory positions defined on a machine.

When using active positions:

  • The scheduler can define the number of active positions when scheduling a production run.
  • The operator can define the number of active positions when starting a production run.

To use active positions:

  • The process type must be configured to create inventory on all positions.
  • A machine on the line must be configured to create inventory.
  • The produced material must have a material form of reel or sheet.
  • The number of active positions cannot exceed the number of inventory positions defined on the machine.
  • The material consumed into the line must have a width must exist in the production order BOM.
  • The produced material must have a width defined.

The application suggests the number of active positions by diving the input material’s width by the output material’s width. However, the user can override the default value with a value that is at least one and less than the number of available positions on the machine.

After a production run starts, the number of active positions cannot be changed. To use a different number of active positions, the production run must be ended and rescheduled.