Starting a scheduled production run
You can execute a planned production run for a production order.
To start a scheduled production run:
- Click Start Next from the operator dashboard. The Start Next window is displayed.
- Specify this information:
- View scheduled Jobs on other Lines
- If enabled, you can start jobs scheduled on other lines that can be executed on the current line.
- Production Order
- The production order to start.
- BOM Variant
- The bill of materials to use for the production order.
- Routing Operation
- The routing operation to execute on the line.
- Line Group
- The line group to assign the production run to.
- Production Instructions
- The instructions of the production order.
- Out Of Sequence Comments
- The comments required when starting an order that is not first in the scheduled sequence.
- Specify this information to return quantity to stock if there are inventory packs being consumed on the running job:
- Position #
- The machine input position on which the inventory pack is consumed.
- Lot
- The lot number of the inventory pack.
- Pack
- The inventory pack being consumed.
- Part #
- The material associated with the inventory pack.
- Description
- The description of the material.
- Quantity
- The quantity of the consumed inventory pack.
- Return Qty
- The quantity to return to stock.
- Unit
- The unit of measure.
- State
- The inventory status assigned to the pack after the return to stock.
- Location
- The storage location to which the inventory pack is returned.
- Click OK.
Note:
- If there is already a production order running and you are starting a new production order, the running production order is automatically ended.
- This option is only available if the line is configured to allow the starting of scheduled production runs.