Reschedule production run on a single line or across multiple lines. To reschedule a production run:
Select Home > To Do > Production Orders. The Production Orders screen is displayed.
Click Reschedule Jobs Based On. The Reschedule Jobs Based On window is displayed.
Specify this information:
Selected Lines / All Lines
Determines whether to reschedule all lines in the plant or selected lines. If the value in this field is set to Selected Lines, you must select the required lines.
First Property
The first property used to determine the production run sequence. If multiple properties are selected, the sequence is a combination of all.
Second Property
The second property used to further refine the production run sequence when additional sorting criteria are required. If multiple properties are selected, the sequence is a combination of all.