Managing a production campaign

You can create production campaigns and assign production orders with sequences.

Adding a production campaign

  1. Select Library > Production Orders > Configuration > Production Campaigns. The Production Campaigns screen is displayed.
  2. Click Add. The Add window is displayed.
  3. Specify the name of the production campaign in the Production Campaign field.
  4. Click OK.

Assigning a production order to production campaign

  1. Select Library > Production Orders > Configuration > Production Campaigns. The Production Campaigns screen is displayed.
  2. Select a production campaign record and click Production Orders. The Production Campaign Orders window is displayed.
  3. Select a production order and click Add. The Add window is displayed.
  4. Specify the sequence of the job within the selected production campaign in the Sequence of job within campaign field.
  5. Click OK.