Creating an overhead order

  1. Select Configuration > Labour > Overhead Orders. The Overhead Orders screen is displayed.
  2. Click Add. The Add window is displayed.
  3. Specify this information:
    Plant
    The manufacturing plant related to the overhead order.
    Overhead Order
    The name of the overhead order.
    Cost Centre
    The cost center associated with the overhead order.
    Description
    The description of the overhead order.
    Overhead Order Status
    The status of the overhead order.
  4. Click OK.