Examples of Replenishment Orders

There are two requests to replenish inventory that exist as replenishment orders:

Replenishment Order Material Request Quantity Move From Move To Pack Pack Quantity
MR00001 Material A 50 Warehouse 1, Rack 32 Production Line 1
MR00002 Material B 100 Warehouse 1, Rack 32 Production Line 2

Replenishment Order MR00001 is fulfilled by delivering inventory pack 10055621:

Replenishment Order Material Request Quantity Move From Move To Pack Pack Quantity
MR00001 Material A 50 Warehouse 1, Rack 32 Production Line 1 10055621 50
MR00002 Material B 100 Warehouse 1, Rack 12 Production Line 2

Replenishment Order MR00002 is partially fulfilled by delivering inventory pack 10033445:

Replenishment Order Material Request Quantity Move From Move To Pack Pack Quantity
MR00001 Material A 50 Warehouse 1, Rack 32 Production Line 1 10055621 50
MR00002 Material B 100 Warehouse 1, Rack 12 Production Line 2 10033445 30
MR00002 Material B 100 Warehouse 1, Rack 12 Production Line 2

It takes a further 3 Inventory Packs to fulfil the quantity:

Replenishment Order Material Request Quantity Move From Move To Pack Pack Quantity
MR00001 Material A 50 Warehouse 1, Rack 32 Production Line 1 10055621 50
MR00002 Material B 100 Warehouse 1, Rack 12 Production Line 2 10033445 30
MR00002 Material B 100 Warehouse 1, Rack 12 Production Line 2 10084521 30
MR00002 Material B 100 Warehouse 1, Rack 12 Production Line 2 10063254 30
MR00002 Material B 100 Warehouse 1, Rack 12 Production Line 2 10088452 10