Splitting production stops

In Infor MES, you can split a production stop, resulting in two production stops for the same total duration.

The two production stops can then be assigned different reasons.

MES Production Downtime Production Stop Split

Each production stop can then be further split, as required.

Note: MES automatically splits a production stop when a production shift ends and a non-working shift begins. Any time in the non-working shift is recorded as excluded time, which is then excluded in OEE calculations. When a non-working shift transitions back into a production shift, the stop automatically reverts.