Splitting production stops
In Infor MES, you can split a production stop, resulting in two production stops for the same total duration.
The two production stops can then be assigned different reasons.
Each production stop can then be further split, as required.
Note: MES automatically splits a production stop when a production shift ends and a non-working shift begins. Any time in the non-working shift is recorded as excluded time, which is then excluded in OEE calculations. When a non-working shift transitions back into a production shift, the stop automatically reverts.