Targets tab

You can specify this information:

Target Time Based On
Indicates the type of target time for the routing operation. Possible values:
  • Target Cycle Time: A target time to produce a specified quantity. If this value is selected, the Target Cycle Time and TCT Qty fields must be specified.
  • Target Fixed Time: A fixed time for the operation regardless of quantity. If this value is selected, the Target Fixed Time field must be specified.
Target Cycle Time
A target time (in seconds) to produce a specified quantity. This field is enabled only if the Target Time Based On field is set to Target Cycle Time option. The Target Cycle Time and TCT Qty fields are mandatory.
TCT Qty
The target quantity of units produced within a defined cycle time. This field is displayed only if the Target Time Based On field is set to Target Cycle Time.
Target Fixed Time
A fixed time for the operation regardless of quantity. This field is displayed only if the Target Time Based On field is set to Target Fixed Time.
Target Setup
The target amount of time required to set up the machine at the start of the operation. If the setup time exceeds the target time, the dashboard prompts the operator to document the reason for the delay.
Target Teardown
The target amount of time required to dismantle the machine at the end of an operation. If the tear down time exceeds the target tear down time, the dashboard prompts the operator to document the reason for the overrun.
Target Ramp Up
The target amount of time required to increase production to the target level. If the ramp up time exceeds the target ramp up time, the dashboard prompts the operator to document the reason for the overrun.
Target Yield
The target yield for the routing operation. This value is expressed as a percentage ranging from 0 to 100.
Target Scrap Rate
The target rate of scrap for the routing operation. This value is expressed as a percentage ranging from 0 to 100.
Planned Labour
The planned number of persons required to perform the routing operation.
Personnel Group
The name of the personnel group that is associated with the operation.
Production Activity Type
The classification of activities carried out related to cost centers.
Production Standard Time
The standard time allocated for staff to complete the production tasks for each unit.
Setup Activity Type
The classification of the setup activity performed for a cost center. This field is used to categorize setup activities for reporting or costing purposes.
Setup Standard Time
A standard time allocated to personnel for setting up each production piece.
Labour Activity Type
The type of labour activity.
Labour Standard Time
The standard labour time required for routing operations, usually provided by the ERP system.
Production Batch Size
The quantity of material generated during each batch of operation.