Example for maintenance procedure

This is an example for configuring a maintenance procedure for blade repairs:

  • Procedure: Blade Repair
  • Work Type: Planned
  • Responsible Department: Maintenance Department
  • Responsible Group: Maintenance Engineers
  • Planned Duration: 4 hours
  • Advance Warning Period: 1 day
  • Maintenance Scheduling Window: 2 days
  • Auto Authorise: Yes
  • Is Compliance Monitored: Yes
  • Planned Machine Downtime: 0
  • Planned Line Downtime: 0
  • Trigger Type: Period
  • Period Type: Days
  • First Due After: 14
  • Second After a Further: 14
  • Then Repeat Every: 14