Adding a maintenance procedure
- Select . The Maintenance Procedures screen is displayed.
- Click Add. The Add window is displayed.
- Specify this information related to the maintenance procedure on the Maintenance Procedure tab:
-
Procedure
-
The name of the procedure.
-
Work Type
-
The type of maintenance work activity performed by the procedure. See, Maintenance work types.
-
Code
-
The code of the procedure.
-
Responsible Department
-
The department responsible for performing the procedure.
-
Responsible Group
-
The personnel group responsible for performing the procedure.
-
Cost Centre
-
The cost center associated with the procedure for financial planning and analysis.
-
Planned Duration
-
The expected time to complete the procedure.
-
Advance Warning Period
-
The timeframe prior to the maintenance date when the planner can view and prepare for upcoming work related to the procedure. This value must be specified if the Is Compliance Monitored check box is selected.
-
Maintenance Scheduling Window
-
The grace period after the planned maintenance date before the work is classified as overdue. This value must be specified if the Is Compliance Monitored check box is selected.
-
Auto Authorise
-
If this check box is selected, the procedure is automatically authorized when scheduled. If this check box is cleared, the procedure must be authorized manually. Maintenance engineers can only execute authorized work.
-
Is Compliance Monitored
-
If this check box is selected, the procedure must be measured for compliance.
-
Planned Machine Downtime
-
The planned period for which the machine is stopped to carry out the procedure.
-
Planned Line Downtime
-
The planned period for which the line is stopped to carry out the procedure.
-
Root Asset
-
The root asset for the procedure, allowing assignment of sub-maintenance procedures within the hierarchical structure of sub assets.
- Specify this information on the Schedule tab:
-
Trigger Type
-
The type of trigger use to trigger the maintenance work. Possible values:
- Period: Schedule the procedure to occur on a periodic basis. A period type as well as frequencies need to be supplied.
- Count: Trigger the procedure based on the usage of an Asset, taken from the Asset Counters. Frequencies need to be supplied.
- Click OK.