Process Type tab

You can specify this information:

Process type
The name for the process type.
Production Mode
The production mode for the process type. Possible values:
  • Standard: A single material is created for the production order.
  • Graded: A single material is created for the production order. However, the created material receives a grading to describe the quality.
  • Expected Co-Production: Multiple materials are created on this production order, using a recipe job. The created material is booked based on pre-defined receiving production orders.
  • Expected Co-Production (Position Restrictions): Multiple materials are created on the production order, using a recipe job. The created material is booked based on pre-defined receiving production orders. However, machine positions must match those on the assigned production orders.
  • Expected Co-Production (Group Restrictions): Multiple materials are created on the production order, using a recipe job. The number of position groups allowed is limited by the Max Value, which defines the number of places in the machine that can create material.
  • Expected Co-Production (Width Restrictions): Multiple materials are created on the production order, using a recipe job. The created material is booked based on the pre-defined receiving production orders.
  • Unexpected Co-Production: Multiple materials are created on the production order, using a recipe job. The created material is booked based on the production orders; however, these orders cannot be pre-defined because the materials created are not expected.
Creates By-Product?
If this check box is selected, by-products are created during the process.
Automatically start a job when scanning inventory
If this check box is selected, a job automatically starts when an inventory pack is scanned for consumption.
Tick if this process should default to rescheduling the remaining quantity as a new job
If this check box is selected, by default the system reschedules the remaining job quantity as a new job when the quantity of the original job is not met.
Can change the BOM linked to the order when start the job?
Determines whether the user can change the Bill of Materials (BOM) linked to the production order when starting a scheduled job. Possible values:
  • Always: Users can always change the BOM.
  • Never: Users cannot change the BOM.
  • Based on Work Order: Users can change the BOM based on the configuration selected when scheduling an order.