Updating a routing operation target

  1. Select Configuration > Materials > Routings. The Routings screen is displayed.
  2. Select a record and click Operations. The Routing Operations screen is displayed at the bottom.
  3. Select a record and click Targets. The Operation Targets screen is displayed at the bottom.
  4. Select the record and click Edit. The Edit window is displayed.
  5. Specify this information:
    Target Cycle Time
    A target time (in seconds) to produce a specified quantity.
    Target Quantity
    The quantity that is associated with the target cycle time.
    Target Setup
    The target amount of time required to set up the machine at the start of the operation. If the setup time exceeds the target, the dashboard prompts the operator to document the reason for the delay.
    Target Teardown
    The target amount of time required to dismantle the machine at the end of an operation. If the teardown time exceeds the target, the dashboard prompts the operator to document the reason for the delay.
    Target Ramp Up
    The time required to ramp up production to the target level. If the actual ramp-up time exceeds the target, the dashboard prompts the operator to provide a reason for the delay.
    Target Yield
    The target yield for the routing operation. This value is expressed as a percentage ranging from 0 to 100.
    Target Scrap Rate
    The target rate of scrap for the routing operation. This value is expressed as a percentage ranging from 0 to 100.
    Planned Labour
    The planned number of persons required to perform the routing operation.