Maintenance projection plan

When a recurring series is defined, MES generates a future-facing projection of all expected maintenance work for each asset. The projection period is set globally, with a default of 730 days (2 years).

Planners can manually adjust orders in the projection plan. Future workload reports include projected schedules for labor, materials, and costs.

Example

This example shows a timeline for 1-year schedule on various assets with different frequencies.

  • Maintenance is scheduled on slitters every 2 weeks.
  • Maintenance is scheduled on packers every 2 months.
  • Maintenance is scheduled on tools every 6 weeks.
  • Maintenance is scheduled on rollers every 5 months.
pic2