Changing the start date or finish date of a long-held MO

You must register a long-held MO before changing the dates because the move is only allowed on long-held manufacturing orders (MO) (status x6).
  1. Start 'Manufact Order. Open' (PMS100/B).
  2. Select the long-held MO to reschedule.
  3. In the 'Related options', select '81- Move long-held MO'.
  4. Specify the new start date or finish date.
  5. Click Enter to display the updated start and finish date on 'Manufact Order. Open' (PMS100/B).