Move long-held manufacturing orders

Use the 'Manufact Order. Open' (PMS100/B) to move the start date or finish date of a long-held manufacturing order (MO).

Limitations

You can only move long-held manufacturing orders (MO) (status x6) on 'Manufact Order. Open' (PMS100/B).

Outcome

When you move a manufacturing order (MO) to a different date, the available capacity is not considered. The component reservation dates, and the operation start and finish dates change by the same number of working days as the adjusted start or finish date.

This table shows the tables affected by the movement of the dates of a long-held MO:
Table Description
MWOHED Stores Manufacturing order header
MWOOPE Contains Manufacturing order operations
MWOMAT Stores Manufacturing order materials
MWOHEH Contains Manufacturing order header for fashion items